Remainder of Budget Period 1
- Determine pattern configuration
- Injectivity testing of CO2 I-1 well
- Final simulation of final configuration with compositional simulator
- Detailed wellbore analysis and document well upgrade plan
- Final budget an plan submitted to DOE
- Summary report and technology transfer