Expanded Project Economics
Total Project – $7.56 million
- $2.34 M – CO2 Purchase, transport, recycling
- $2.21 M – Research, Technology Transfer
- $1.33 M – Capital Costs (wells, etc.)
- $1.68 M – Operations (8 years)
-
Funding
- $2.03 M MV Energy
- $0.52 M Kinder-Morgan CO2 Co. LP
- $0.97 M ICM
- $2.77 M U.S. Department of Energy
- $1.17 M KGS and TORP
- $0.10 M Kansas Department of Commerce